4 Commits

Author SHA1 Message Date
Hartmut 8c9ba5363c docs: mark P1 timeline/SSE/scenario work complete in plan and roadmap
All Workstream C–F tasks completed:
- C: drag+selection conflict fix (FloatingActionBar clears on drag start)
- D: SSE edge-case tests (hide-during-reconnect, first-ever-failure)
- E: scenario module unit tests — 31 tests across all 4 scenario modules
- F: .env.example expanded, plan and roadmap updated

Co-Authored-By: claude-flow <ruv@ruv.net>
2026-04-02 21:34:15 +02:00
Hartmut 47e4d701ff chore(repo): checkpoint current capakraken implementation state 2026-03-29 12:47:12 +02:00
Hartmut 625a842d89 feat: dashboard overhaul, chargeability reports, dispo import enhancements, UI polish
Dashboard: expanded chargeability widget, resource/project table widgets
with sorting and filters, stat cards with formatMoney integration.

Chargeability: new report client with filtering, chargeability-bookings
use case, updated dashboard overview logic.

Dispo import: TBD project handling, parse-dispo-matrix improvements,
stage-dispo-projects resource value scores, new tests.

Estimates: CommercialTermsEditor component, commercial-terms engine
module, expanded estimate schemas and types.

UI: AppShell navigation updates, timeline filter/toolbar enhancements,
role management improvements, signin page redesign, Tailwind/globals
polish, SystemSettings SMTP section, anonymization support.

Tests: new router tests (anonymization, chargeability, effort-rule,
entitlement, estimate, experience-multiplier, notification, resource,
staffing, vacation).

Co-Authored-By: claude-flow <ruv@ruv.net>
2026-03-14 23:29:07 +01:00
Hartmut dd55d0e78b chore(repo): initialize planarchy workspace 2026-03-14 14:31:09 +01:00