Hartmut 92a982b151 feat: Nearshore-Ratio indicator per project
Engine (packages/engine):
- calculateShoringRatio() pure function: onshore/offshore hours,
  country breakdown, threshold check, weighted by hours not headcount
- 12 unit tests: empty, 100% onshore/offshore, mixed ratios,
  custom threshold, case-insensitive, unknown country, FTE weighting

Schema:
- Project.shoringThreshold (default 55%) — per-project configurable
- Project.onshoreCountryCode (default "DE") — configurable onshore country

API (project router):
- getShoringRatio query: loads assignments with resource.country,
  computes ratio, returns full breakdown
- update mutation: accepts shoringThreshold + onshoreCountryCode

UI:
- ShoringIndicator: stacked horizontal bar with country segments,
  severity badge (green/yellow/red), hover tooltip, dark theme
- ShoringBadge: mini colored dot + % for project list column
- ProjectModal: "Max Offshore %" number input
- Project detail: indicator after budget status card
- Project list: "Shoring" column (default hidden, toggleable)

AI Assistant:
- get_shoring_ratio tool: human-readable breakdown with threshold alert

Colors: green (<threshold-10), yellow (threshold-10 to threshold), red (>=threshold)
Default: 55% offshore threshold, "DE" as onshore country

Co-Authored-By: claude-flow <ruv@ruv.net>
2026-03-26 11:45:50 +01:00

178 lines
7.4 KiB
Markdown

# Nearshore-Ratio Indikator — Plan
## Anforderungsanalyse
**Was:** Ein Nearshore/Offshore-Ratio Indikator pro Projekt, der zeigt wieviel % der gebuchten Ressourcen Standort Deutschland vs. andere Standorte haben.
**Kernkonzept:**
- **Onshore** = Resource hat `countryId` → Country mit Code "DE" (Deutschland)
- **Offshore/Nearshore** = Resource hat `countryId` → Country mit Code != "DE" (oder kein Country gesetzt)
- **Shoring-Ratio** = (Offshore-Stunden / Gesamt-Stunden) * 100
- **Threshold** = Default 55%, pro Projekt aenderbar
- **Anzeige** = Farbiger Indikator (gruen < Threshold, rot >= Threshold)
**Datenquelle:** Assignments eines Projekts → Resource.countryId → Country.code
---
## Betroffene Pakete & Dateien
| Paket | Dateien | Art der Aenderung |
|-------|---------|------------------|
| `packages/db` | `prisma/schema.prisma` | **edit**`shoringThreshold Int?` auf Project |
| `packages/engine` | `src/allocation/shoring-ratio.ts` | **create** — Pure Berechnung |
| `packages/engine` | `src/__tests__/shoring-ratio.test.ts` | **create** — Unit Tests |
| `packages/api` | `src/router/project.ts` | **edit**`getShoringRatio` Query + Threshold im Update |
| `packages/api` | `src/router/assistant-tools.ts` | **edit**`get_shoring_ratio` AI Tool |
| `apps/web` | `src/components/projects/ShoringIndicator.tsx` | **create** — Visueller Indikator |
| `apps/web` | `src/app/(app)/projects/[id]/page.tsx` | **edit** — Indikator auf Detail-Seite |
| `apps/web` | `src/app/(app)/projects/ProjectsClient.tsx` | **edit** — Indikator-Spalte in Projektliste |
| `apps/web` | `src/components/projects/ProjectModal.tsx` | **edit** — Threshold-Feld im Edit |
| `apps/web` | `src/components/dashboard/widgets/ProjectHealthWidget.tsx` | **edit** — Optional: Shoring in Health-Score |
---
## Task-Liste
### Phase 1: Schema + Engine (sequenziell)
- [ ] **Task 1:** Schema erweitern → `packages/db/prisma/schema.prisma`
- `shoringThreshold Int? @default(55)` auf dem Project Model
- Repraesntiert den kritischen Shoring-Prozentsatz (Default 55%)
- `prisma db push`
- [ ] **Task 2:** Pure Shoring-Ratio Berechnung → `packages/engine/src/allocation/shoring-ratio.ts`
```typescript
interface ShoringInput {
resourceId: string;
countryCode: string | null; // "DE", "ES", "IN", etc.
hoursPerDay: number;
workingDays: number; // oder totalHours direkt
}
interface ShoringResult {
totalHours: number;
onshoreHours: number; // countryCode === "DE"
offshoreHours: number; // countryCode !== "DE"
offshoreRatio: number; // 0-100 (%)
onshoreRatio: number; // 0-100 (%)
threshold: number; // Default 55
isAboveThreshold: boolean;
byCountry: Record<string, { hours: number; pct: number; resourceCount: number }>;
}
export function calculateShoringRatio(
assignments: ShoringInput[],
threshold?: number, // Default 55
onshoreCountryCode?: string, // Default "DE"
): ShoringResult
```
- [ ] **Task 3:** Unit Tests → `packages/engine/src/__tests__/shoring-ratio.test.ts`
- 100% Deutsche Ressourcen → offshoreRatio = 0, isAboveThreshold = false
- 100% Offshore → offshoreRatio = 100, isAboveThreshold = true
- 50/50 Mix → offshoreRatio = 50, isAboveThreshold = false (< 55)
- 60/40 Mix → offshoreRatio = 60, isAboveThreshold = true (> 55)
- Custom Threshold (30%) → 40% Offshore = above threshold
- Leere Assignments → offshoreRatio = 0
- Resource ohne Country → zaehlt als Offshore
- [ ] **Task 4:** Export → `packages/engine/src/allocation/index.ts`
### Phase 2: API + UI (parallel)
- [ ] **Task 5:** API Query → `packages/api/src/router/project.ts`
- `getShoringRatio` Query (protectedProcedure):
- Input: `{ projectId: string }`
- Laedt Assignments mit Resource.country
- Ruft `calculateShoringRatio()` auf
- Returns: `ShoringResult`
- `update` Mutation erweitern: `shoringThreshold` im Input akzeptieren
- `getById` erweitern: `shoringThreshold` im Response zurueckgeben
- [ ] **Task 6:** Visueller Indikator → `ShoringIndicator.tsx`
- Kompakte Anzeige:
```
[====DE 45%====|==ES 30%==|IN 25%] ⚠ 55% offshore (Limit: 55%)
```
- Stacked horizontal bar: Laender-Segmente farbig
- Gruen/Gelb/Rot Badge je nach Threshold
- Gruen: < Threshold - 10pp
- Gelb: Threshold - 10pp bis Threshold
- Rot: >= Threshold
- Tooltip: Aufschluesselung nach Land
- Props: `projectId: string` (laedt Daten selbst via tRPC)
- [ ] **Task 7:** Threshold im ProjectModal → `ProjectModal.tsx`
- Neues Feld: "Max Offshore %" (Number Input, 0-100, Default 55)
- Unter "Budget" oder als eigene Section "Shoring"
- Label: "Maximum Offshore/Nearshore Ratio (%)"
- Hinweis: "Alert when offshore staffing exceeds this percentage"
- [ ] **Task 8:** Indikator auf Projekt-Detail-Seite → `projects/[id]/page.tsx`
- `<ShoringIndicator projectId={id} />` neben dem Budget-Status
- Oder als eigene Karte unter den Budget-Karten
- [ ] **Task 9:** Indikator-Spalte in Projektliste → `ProjectsClient.tsx`
- Neue Spalte "Shoring" mit Mini-Indikator (nur Badge gruen/gelb/rot + %)
- InfoTooltip: "Offshore staffing ratio vs project threshold"
### Phase 3: AI + Dashboard (parallel)
- [ ] **Task 10:** AI Assistant Tool → `assistant-tools.ts`
- `get_shoring_ratio` Tool:
- Input: `{ projectId: string }`
- Returns: menschenlesbare Aufschluesselung
- "Project X: 45% onshore (DE), 55% offshore (ES 30%, IN 25%). ⚠ Above 55% threshold."
- [ ] **Task 11:** Optional: Dashboard Widget oder ProjectHealth Integration
- Shoring-Warnung in ProjectHealthWidget einbauen
- Oder neues Mini-Widget "Shoring Alerts" (Projekte ueber Threshold)
---
## Abhaengigkeiten
```
Task 1 (Schema) → Task 2 (Engine) → Task 3 (Tests) → Task 4 (Export)
Task 4 → Task 5 (API)
Task 5 → Task 6 + Task 7 + Task 8 + Task 9 (alle parallel)
Task 5 → Task 10 (AI Tool)
Task 5 → Task 11 (Dashboard)
```
- Tasks 6-9 **vollstaendig parallel** (verschiedene Dateien)
- Tasks 10-11 parallel zu Tasks 6-9
---
## Akzeptanzkriterien
- [ ] `pnpm test:unit` laeuft gruen (inkl. neue shoring-ratio Tests)
- [ ] `pnpm --filter @planarchy/web exec tsc --noEmit` — keine neuen Errors
- [ ] **Projekt-Detail:** Shoring-Indikator sichtbar mit Laender-Aufschluesselung
- [ ] **Projektliste:** Shoring-Badge-Spalte (gruen/gelb/rot)
- [ ] **Projekt-Edit:** Threshold aenderbar (Default 55%)
- [ ] **AI Assistant:** "Wie ist der Shoring-Mix bei Projekt X?" liefert Antwort
- [ ] **Farben:** Gruen < 45%, Gelb 45-55%, Rot >= 55% (bei Default-Threshold)
- [ ] **Resource ohne Country:** Zaehlt als Offshore
- [ ] **Projekt ohne Assignments:** Zeigt "No data" statt Fehler
---
## Risiken & offene Fragen
### Risiken
- **Country-Daten unvollstaendig:** Viele Resources haben moeglicherweise kein `countryId` gesetzt
→ Mitigation: Zaehlt als Offshore + Warning "X resources have no country assigned"
- **Stunden vs Headcount:** Soll nach Stunden oder Koepfen gemessen werden?
→ Vorschlag: Stunden (gewichtet), da ein 50%-FTE weniger zaehlt als ein 100%-FTE
### Offene Fragen
1. **Nur "DE" als Onshore?** Oder soll der Onshore-Laendercode konfigurierbar sein?
→ Vorschlag: Default "DE", aber konfigurierbar pro Projekt
2. **Welche Assignment-Status zaehlen?** Nur CONFIRMED? Auch PROPOSED?
→ Vorschlag: CONFIRMED + PROPOSED (beide relevant fuer Planung)
3. **Soll der Indikator auch in der Timeline sichtbar sein?**
→ Vorschlag: Erst mal nur Projektliste + Detail-Seite